Hi All,

I'm trying to set up a Make to Order scenario.

I have set up my product as Procurement Method = Make to Order and Supply Method = Buy.

Against the product I have also set up a supplier with a delivery lead time of 60 and a minimal quntity of 1.

I then create a sales order for the product and confirm the sale.  If I check the Purchase order and Quotations I dont see anything created.

When I go back into the sales order and view delivery and use Check Availability the product shows as Waiting Availability.  If I check the Purchase order and Quotations I dont see anything created.

At what point is the Purchase order or Quotation raised, do I have to run the Run Schedulers each time to generate the Purchase or have I missed some configuration or setting which allows the Purchase to be generated when the sales order is confirmed?