Hi, I am testing OpenERP 7.0 warehouse and manufacturing functionalities and I have set product and BOM for it which has two levels (there is one intermediate structure below main level) but it seems that OpenERP calculates material demands only for first level. Is there some setting somewhere which could affect to this? (OpenERP calculates and processes the demands also for the second level)
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- CRM
- e-Commerce
- Accounting
- Inventory
- PoS
- Project management
- MRP
This question has been flagged
Hmm.. how it can be done, because MO (manufacturing order) is on the production side and Run schedulers functionality is in warehouse side? I do not see any option for this in manufacturing order.
I have two intermediate structures (on the second level in BOM) there which should be manufactured in the house, but at the moment system does not calculate material demands for manufacturing of these two ntermediate structures.
Seems to be working now.. it seems that I had minor fail in material settings
Have you tried running the scheduler again (ie: once per level) ?