Is there a way to distribute workload among multiple work centers?

For example, there are 5 work centers, each representing a mounting machine.

There is a demand of qty 600 for the finished product, and I'd like Odoo to split the manufacturing orders and work orders so that Odoo generates 5 sets of these orders each processing qty 120 (given those machines are equally available).

Would be nice to hear examples of handling this kind of scenario.

0
Balázs Nagy
On 1/5/18, 4:55 AM

This is something I am looking for currently. What is the forum for future feature request?


Our example: we use driers. The different articles occupy them for different amount of hours. Would be nice to plan and log their workload with Odoo.

About This Community

This platform is for beginners and experts willing to share their Odoo knowledge. It's not a forum to discuss ideas, but a knowledge base of questions and their answers.

Register

Odoo Training Center

Access to our E-learning platform and experience all Odoo Apps through learning videos, exercises and Quizz.

Test it now

Question tools

3 follower(s)

Stats

Asked: 1/7/17, 10:51 PM
Seen: 838 times
Last updated: 1/5/18, 4:56 AM