I would like to know the reason why the Mark as done button of the production is enabled when all the work orders end without taking into account the stock of the components.


I have a route that consumes all the components in the first work order. Well, even without having stock, the work order is marked as done and when the rest of the orders are finished, the production can also be marked as done. Finally, the stock of the components remain negative in my warehouse.

アバター
破棄
最善の回答

It simply let an employe to be able to confirm a Work Order in the case there is an error in stock quantity.  Lets suppose the raw component are realy into his hand and he can realy complete the work order... Its a better way to let him confirm the WO and make an inventory ajustement later...