So in summary order parts, receipt/validate of parts but on receipt/validation they're booked to a project and not showing on stock or available.  And no value added to stock just the project number for reporting purposes.



アバター
破棄
最善の回答

Create a location for each Project that is of type Inventory Loss with a Stock Valuation Account (Incoming) account configured to offset the value of inventory "lost" during the move to this location.

Move your products to this location instead of the regular Stock location when you process the Receipt (or after via an Internal Transfer if you forget).

Consult your Bookkeeper or Accountant ​to understand which account to use and inform them they will need to move this amount out as it represents additional project costs.

アバター
破棄
著作者 最善の回答

Thanks Ray :)