hi,

I am experimenting with project managment Module since a little while and find it not very workable.

  1. the gantt view does not show the current date (so you don't have a good idea where you actually are in a project)
  2. gantt view randomly shows the bars for tasks filled or empty or half filled (I guess this should indicate the completion status) so this is pretty useless

At the moment I wonder whether I just don't get how to use it or whether it is just a half-baked module ... or a demo-version

Is anyboyd using Project management really? Any best-practise or how-to's would be very helpfull. What I have found so far (youtube i.e.) do not get into any detail and seem to be made of people who never used this Module in real life