We produce cable on drums. Each drum with cable is one unique lot number.  In a manufacturing order you can only manufacture one lot number. 

We have an annealing process at the end (for some products).  In the annealing facility you put many drums (= many lot numbers), and process those at the same time.  There are several QA registrations also to register.

Any tips on how to set this up efficiently?

アバター
破棄
著作者

I got an idea for solution: When setting order status finish, divide the cost for this operation by the number of backorders. Should be possible with a server action. Hmm.
Need to speak to my developer.

It helps to discuss.

Did you find a solution for this?

Hi Lars. Were you able to solve this issue? I manufacture rolls of paper, similar to your drums of cable, and I'm running into the same issue.

最善の回答

In Odoo 19.0 it is now possible to manufacturing multiple Lots or Serial Numbers from a single Manufacturing Order.