Hi,

i have some problem when i am using a MTO to generate autamatically RFQ from production order. (or thing wich i want to do is impossible:)

When i make a PO for 5 pcs. of my product the quantity of components on material list is ok. (components are correct for 5 pcs. to produce).


When i push the "Done" buton, purchase (RFQ) is generated also with correct amount of components.

But if in this moment i use a "Mass Produce" button i have this message:

" Make sure enough quantities of these components are reserved to carry on production: "


It is some mistake in my configuration, or it is impossible to create a mass production with automatic rfq in this way?


Thx for help.