What is the use of the button `PUBLISH` in project planning?

Here is the scenario i am trying.

  1. Created a project

  2. Created a task without assigning a user

  3. Created project planning

  4. Assigned a role, time estimate and assign the employee

  5. And hit on the PUBLISH button.

I thought the task will be assigned to the employee. But unfortunately, it didn't happen.

Is it possible to assign a task from the project planning?

And what is happening when i hit on the `PUBLISH` button?



อวตาร
ละทิ้ง
คำตอบที่ดีที่สุด

Hi,

The planning enables you to organize your team by roles however tasks can only be assigned to internal users.

In the following link a explanation for the Publish feature.

BR

Ricardo

อวตาร
ละทิ้ง
ผู้เขียน

That means, there is no impact in task assigning when planning publish, right?

An employee has to assign themselves the task in a shift, right?