We work in a very fluid manufacturing environment where we may have several different BOMs for making a product depending on the raw materials, and equipment available.  

I'm looking for a method to change to a different BOM after an MO is confirmed. I've tried setting the BOM field to allow modifying but get errors

It seems as if adding the ability to "Reset to Draft" like an invoice would work.  Can I use a server action to achieve this?

Аватар
Отменить
Лучший ответ

HI 

I Suggest 2 Solution 

1st through Quality Check types ( Register consumed Materials ) in specific MO order and validate it 

2nd Through PLM Module will make an engineering changes in Product BOM In general

Аватар
Отменить

Are you saying that we should enable Quality Checks? Or through PLM, no, I don't understand that one at all. Could you provide more info or examples?