When using manufacturing in Odoo16,how does the system calculate the scheduled date and scheduled end date when clicking on the 'planned' button? I'm looking for insights into the process behind determining the scheduled date to better understand the workflow.
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- CRM
- e-Commerce
- Boekhouding
- Voorraad
- PoS
- Project
- MRP
Deze vraag is gerapporteerd
It calculate the time necessary to manufacture the planned qty from the time set in the operation in the BOM. The time is what it take to manufacture 1 pcs.
It will schedule the start date according to the schedule date on the manufacturing order, for the fist available time slot long enough to complete the order. If the schedule date is in the past, it will look from today and forward.
Geniet je van het gesprek? Blijf niet alleen lezen, doe ook mee!
Maak vandaag nog een account aan om te profiteren van exclusieve functies en deel uit te maken van onze geweldige community!
AanmeldenGerelateerde posts | Antwoorden | Weergaven | Activiteit | |
---|---|---|---|---|
|
0
mrt. 25
|
984 | ||
|
0
aug. 25
|
136 | ||
|
0
aug. 25
|
133 | ||
|
2
aug. 25
|
648 | ||
Automatic Batch Transfer
Opgelost
|
|
1
aug. 25
|
463 |