When using manufacturing in Odoo16,how does the system calculate the scheduled date and scheduled end date when clicking on the 'planned' button? I'm looking for insights into the process behind determining the scheduled date to better understand the workflow.
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- CRM
- e-Commerce
- Contabilidad
- Inventario
- PoS
- Project
- MRP
Se marcó esta pregunta
It calculate the time necessary to manufacture the planned qty from the time set in the operation in the BOM. The time is what it take to manufacture 1 pcs.
It will schedule the start date according to the schedule date on the manufacturing order, for the fist available time slot long enough to complete the order. If the schedule date is in the past, it will look from today and forward.
¿Le interesa esta conversación? ¡Participe en ella!
Cree una cuenta para poder utilizar funciones exclusivas e interactuar con la comunidad.
InscribirsePublicaciones relacionadas | Respuestas | Vistas | Actividad | |
---|---|---|---|---|
|
0
mar 25
|
969 | ||
|
0
ago 25
|
120 | ||
|
0
ago 25
|
116 | ||
|
2
ago 25
|
632 | ||
Automatic Batch Transfer
Resuelto
|
|
1
ago 25
|
458 |