Overslaan naar inhoud
Menu
Je moet geregistreerd zijn om te kunnen communiceren met de community.
Deze vraag is gerapporteerd
1 Beantwoorden
1707 Weergaven

Hello, is there the option to see the activity reporting listed by the scheduled activity date? The  standard  shows  the completion day, however  i t happens very often that users mark as done the activity later that it has actually happened, or even input a new scheduled activity in the past, so the completion day is not enough to see what my team is doing and when.


Avatar
Annuleer
Beste antwoord

Enable developer  mode  Goto -> Settings->Activities ->Group by created on


Avatar
Annuleer