Hello, is there the option to see the activity reporting listed by the scheduled activity date? The  standard  shows  the completion day, however  i t happens very often that users mark as done the activity later that it has actually happened, or even input a new scheduled activity in the past, so the completion day is not enough to see what my team is doing and when.


Avatar
Vazgeç
En İyi Yanıt

Enable developer  mode  Goto -> Settings->Activities ->Group by created on