Se rendre au contenu
Menu
Cette question a été signalée
1 Répondre
5301 Vues

Hello everyone,

If I make run schedulers on my make to stock product nothing happend in my Purchase quatation.

1. I have created the product so its not that

2. I have created the supplier.

3. My local stock is ok... i know he shoud creat a draf because I go 0 product on it

What should i look for ..... 

 

Avatar
Ignorer
Meilleure réponse

Actually I am not so sure about your question, I hope the following can help you.

https://www.odoo.com/apps/7.0/mrp_jit/

This module allows Just In Time computation of procurement orders.

If you install this module, you will not have to run the regular procurement scheduler anymore (but you still need to run the minimum order point rule scheduler, or for example let it run daily). All procurement orders will be processed immediately, which could in some cases entail a small performance impact.

It may also increase your stock size because products are reserved as soon as possible and the scheduler time range is not taken into account anymore. In that case, you can not use priorities any more on the different picking.

Avatar
Ignorer
Publications associées Réponses Vues Activité
0
mars 15
4460
2
sept. 21
7468
8
juin 19
4993
1
août 25
205
0
juil. 25
354