Přejít na obsah
Menu
You need to be registered to interact with the community.
This question has been flagged
1 Odpovědět
5252 Zobrazení

Hello everyone,

If I make run schedulers on my make to stock product nothing happend in my Purchase quatation.

1. I have created the product so its not that

2. I have created the supplier.

3. My local stock is ok... i know he shoud creat a draf because I go 0 product on it

What should i look for ..... 

 

Avatar
Zrušit
Nejlepší odpověď

Actually I am not so sure about your question, I hope the following can help you.

https://www.odoo.com/apps/7.0/mrp_jit/

This module allows Just In Time computation of procurement orders.

If you install this module, you will not have to run the regular procurement scheduler anymore (but you still need to run the minimum order point rule scheduler, or for example let it run daily). All procurement orders will be processed immediately, which could in some cases entail a small performance impact.

It may also increase your stock size because products are reserved as soon as possible and the scheduler time range is not taken into account anymore. In that case, you can not use priorities any more on the different picking.

Avatar
Zrušit
Related Posts Odpovědi Zobrazení Aktivita
0
bře 15
4379
2
zář 21
7375
8
čvn 19
4918
0
čvc 25
354
2
čvn 25
1257