Hello... I'm on Odoo 17.
I have BoM that triggers a sub-assembly in another BoM and that BoM triggers another sub-assembly.
For example, BoM for a table with wheelie legs triggers the sub-assembly of the wheelie legs. Also, we need to assemble the wheels. All of these products are Manufacture/MTO.
Also note: these MOs are triggered by a sales order.
When I plan these MOs...the wheels are scheduled after the wheelie legs and tables. That does not make sense.
Odoo seems to understand that these MOs are linked. I see this on the Component Status on the Manufacturing Order page reflect it. Plus, I see the red triangle Wheelie Leg MO.
Not: unplanning and planning does not push the MOs to the right order.
The question is... how can I force the dependency among multiple MOs?
Please, can anyone answer this? It seems to be a big flaw, isnt it?