Hello...  I'm on Odoo 17.


I have BoM that triggers a sub-assembly in another BoM and that BoM triggers another sub-assembly.


For example, BoM for a table with wheelie legs triggers the sub-assembly of the wheelie legs. Also, we need to assemble the wheels. All of these products are Manufacture/MTO.


Also note: these  MOs are triggered by a sales order. 


When I plan these MOs...the wheels are scheduled after the wheelie legs and tables. That does not make sense.

Odoo seems to understand that these MOs are linked. I see this on the Component Status on the Manufacturing Order page reflect it. Plus, I see the red triangle Wheelie Leg MO. 


Not: unplanning and planning does not push the MOs to the right order.


The question is... how can I force the dependency among multiple MOs?


Avatar
Zrušit

Please, can anyone answer this? It seems to be a big flaw, isnt it?