Ir al contenido
Menú
Se marcó esta pregunta
1 Responder
2332 Vistas

Hello,

How can I automate the status update of a parent task?

I would like the parent task to be updated to "done" when all its blocking subtasks are done.

Is it possible?

Thank you for your help!

Avatar
Descartar
Mejor respuesta

You could try this:

Settings > Techincal > Automated Actions:

Model: Task
Trigger: On Update
Trigger Fields: Blocked By
Before Update Domain: Blocked By > Stage > Name = "in progress"
Domain: Blocked By > Stage > Name = "done"
Action To Do: Update the Record

Data to Write:
Field: Stage (project.task)
Evaluation Type: Reference
Record: Done

Avatar
Descartar
Publicaciones relacionadas Respuestas Vistas Actividad
2
may 25
391
1
abr 20
2055
2
sept 23
2112
2
may 17
7539
2
mar 24
1548