Hello,

How can I automate the status update of a parent task?

I would like the parent task to be updated to "done" when all its blocking subtasks are done.

Is it possible?

Thank you for your help!

Avatar
Zrušit
Nejlepší odpověď

You could try this:

Settings > Techincal > Automated Actions:

Model: Task
Trigger: On Update
Trigger Fields: Blocked By
Before Update Domain: Blocked By > Stage > Name = "in progress"
Domain: Blocked By > Stage > Name = "done"
Action To Do: Update the Record

Data to Write:
Field: Stage (project.task)
Evaluation Type: Reference
Record: Done

Avatar
Zrušit