I have a bom defined with 2 operations. Each takes 10 minutes and uses a different work center. When a customer orders 50 of these products, the planner schedules all 50 of operation 1 (taking 500 minutes) followed by 50 of operation 2, meaning it takes almost 1000 minutes before the first product is ready. How do I get it to schedule them in parallel? The entire order should be complete in 510 minutes.
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- CRM
- e-Commerce
- Contabilidad
- Inventario
- PoS
- Project
- MRP
Se marcó esta pregunta
1402
Vistas
¿Le interesa esta conversación? ¡Participe en ella!
Cree una cuenta para poder utilizar funciones exclusivas e interactuar con la comunidad.
Inscribirse
Oops. 510 minutes for the first to be ready, not 1000. But it should be done in 20 minutes.