I have a bom defined with 2 operations. Each takes 10 minutes and uses a different work center. When a customer orders 50 of these products, the planner schedules all 50 of operation 1 (taking 500 minutes) followed by 50 of operation 2, meaning it takes almost 1000 minutes before the first product is ready. How do I get it to schedule them in parallel? The entire order should be complete in 510 minutes.

아바타
취소
작성자

Oops. 510 minutes for the first to be ready, not 1000. But it should be done in 20 minutes.