The reordering rules trigger only for just in time replenishment, is there a way in odoo CE and EE to tell it to check for, lets say, the whole week and reorder what will be needed today?

Example: I have a "product A" set as Reordering Rules (RR) 5/0/0, and 5 units on stock.

On Monday I recive a SO for 25 units. Shipping for next Monday.

On Tuesday I recive another SO for 25 units. Shipping for next Tuesday.

On Wednesday I want to send the PO for the required 50 units, but since the date has not been triggered yet odoo does not recomand me to purchase anything, but I do know I'll need those 50 units. I want odoo to check all pending operations till next week (or 10 days, or whatever) and prepare the POs and MOs already.

Is there a way to achive this on base odoo CE and EE? If not, is there any custom module?


Avatar
Verwerfen
Beste Antwort

In the reordering rules you have the field Visibility.   Use this field to combine several requirements.   Lead time for purchase, both Security lead time and delivery time on the vendor have impact.

Avatar
Verwerfen
Autor Beste Antwort

I ended up setting a Security Lead Time for Purchase of 1 year.

Now I get the POs created at the moment.