I am trying to add start data and end date to a task, but I can't see the fields in on the Extra Info tab.

Avatar
Verwerfen
Beste Antwort

Extended view in v7 is done by going to the users preferences and clicking on 'Technical Features' in the 'Access Rights' tab.

Avatar
Verwerfen

No changes in views....

Beste Antwort

This works in OpenERP v6.0 and 6.1, but not work any more in v7. The correct way to do that in v7 is http://help.openerp.com/question/7650/how-to-activate-the-technical-features/ (here)