In the manufacturing module I'm trying to utilize the work order planning to actively schedule the daily activities in a job shop manufacturing environment.  As often happens in a job shop, priorities, due dates, and available resources change.  If a sequence isn't completed when estimated the projected complete and the subsequent operations need to get pushed out. 

How does one work with the planning module to actively schedule/reschedule the planned work?