Hello friends, 

I have a configuration problem and I don't know if it's complicated to perform

In my company we work with castors CASTOR1 and it has a BOM (FORK1 and WHEEL1) something similar to the wheel of a bicycle.

Well then CASTOR1 can be buy directly from the supplier or I can also buy both parts (support1 and wheel1) and manufacture them.

For example: In my warehouse, we have CASTOR1 (5000 units), FORKS1 (2000 units) and WHEEL1 (2500 units)

If i have a SO 6000 wheels -> how could configure the routes so that the system automatically generates a MO of 1000 units of CASTOR1?

Currently the system generates the automatic MO but of the 6000 wheels :(


Thanks in advance