How to calculate Half day leave in Open ERP.I have specified the date as 02/02/2014 9.00 to 13.00 in Duration field,the no of days as 0.5.But it is calculated as full day leave only.How to fix it?

頭像
捨棄
最佳答案

The below patch Fixed the Issues to show the days calculated in 0.5 based on From and To date.

Example: 02/02/2014 9.00 to 13.00 in Duration field,the no of days as 0.5

https://gist.github.com/tejastank/5089560#file-hr_holidays_leave_correction-patch