Hi Folks,

I am using odoo 10 and critical situation is that 62 schedulers are running and 27 of 62 are running at interval of  1 minute. one or more than one some scheduler gone stuck. Friends suggest me any alternative to sort out this problem to run odoo smoothly.

Every suggestion will be appreciate.

Regards,

Akhilesh Gupta

頭像
捨棄
最佳答案

You need to follow below steps.

1. Configure Worker in server as per server resources.

2. Create multiple users for schedulers and assign different users in schedulers. ( Do not execute all scheduler with same users)

3. Increase max_cron_threads(Maximum number of threads processing concurrently cron jobs) in config file as per server configuration.