İçereği Atla
Menü
Bu soru işaretlendi
1 Cevapla
2110 Görünümler

Hi Folks,

I am using odoo 10 and critical situation is that 62 schedulers are running and 27 of 62 are running at interval of  1 minute. one or more than one some scheduler gone stuck. Friends suggest me any alternative to sort out this problem to run odoo smoothly.

Every suggestion will be appreciate.

Regards,

Akhilesh Gupta

Avatar
Vazgeç
En İyi Yanıt

You need to follow below steps.

1. Configure Worker in server as per server resources.

2. Create multiple users for schedulers and assign different users in schedulers. ( Do not execute all scheduler with same users)

3. Increase max_cron_threads(Maximum number of threads processing concurrently cron jobs) in config file as per server configuration.

Avatar
Vazgeç
Üretici

Any process to configure worker in server as per server resources? Currently system running on 16 core processor, also explain how can differently assign different scheduler?