Security lead time for purchase does not seem to work

Avatar
Annuleer

hi, it works, but not good. it works to the past. put security days with '-'

Auteur

Do you happen to know why it does not work , is it a bug?

even with "- " it does not work


Beste antwoord

Hi,

To account for unforeseen vendor delays, the system will produce Purchase Orders for product procurement that are many days earlier than intended.

Please refer to the blog given below:

https://www.cybrosys.com/blog/how-to-manage-lead-time-in-odoo-16


Hope it helps