How can I indicate that a task cannot start until another task finishes
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- CRM
- e-Commerce
- Contabilità
- Magazzino
- PoS
- Project
- MRP
La domanda è stata contrassegnata
Hello!
That is not possible out of the box. You might be able to develop something with Studio, but that would still require Python coding. Another solution (if you on-premise or on .sh), could be trying to use a third party app such as: https://apps.odoo.com/apps/modules/13.0/project_task_dependency/.
I hope I helped :)
Have a great day!
Cheers,
Odoo eLearning team.
Thank you very much for your answer. I'll be reviewing your directions.
You could try out our solution for this question, it handles constraints between tasks.
https://apps.odoo.com/apps/modules/14.0/bryntum_gantt/
Ti stai godendo la conversazione? Non leggere soltanto, partecipa anche tu!
Crea un account oggi per scoprire funzionalità esclusive ed entrare a far parte della nostra fantastica community!
RegistratiPost correlati | Risposte | Visualizzazioni | Attività | |
---|---|---|---|---|
|
1
lug 25
|
558 | ||
|
2
giu 25
|
2490 | ||
|
1
giu 25
|
943 | ||
|
3
mag 25
|
2449 | ||
Install your own modules in Odoo
Risolto
|
|
2
lug 25
|
1438 |