لقد تم الإبلاغ عن هذا السؤال
Hello!
That is not possible out of the box. You might be able to develop something with Studio, but that would still require Python coding. Another solution (if you on-premise or on .sh), could be trying to use a third party app such as: https://apps.odoo.com/apps/modules/13.0/project_task_dependency/.
I hope I helped :)
Have a great day!
Cheers,
Odoo eLearning team.
Thank you very much for your answer. I'll be reviewing your directions.
You could try out our solution for this question, it handles constraints between tasks.
https://apps.odoo.com/apps/modules/14.0/bryntum_gantt/
هل أعجبك النقاش؟ لا تكن مستمعاً فقط. شاركنا!
أنشئ حساباً اليوم لتستمتع بالخصائص الحصرية، وتفاعل مع مجتمعنا الرائع!
تسجيلالمنشورات ذات الصلة | الردود | أدوات العرض | النشاط | |
---|---|---|---|---|
|
1
يوليو 25
|
558 | ||
|
2
يونيو 25
|
2489 | ||
|
1
يونيو 25
|
942 | ||
|
3
مايو 25
|
2443 | ||
Install your own modules in Odoo
تم الحل
|
|
2
يوليو 25
|
1435 |