In project module I am using Automated Actions to "blocked" task Status
when move Tasks Stages to "Done"
but it no working
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- CRM
- e-Commerce
- Contabilità
- Magazzino
- PoS
- Progetti
- MRP
La domanda è stata contrassegnata
Hi,
You have almost done it. You have to use the field Stage(stage_id) instead of Closing Stage(is_closed) in Trigger Fields. Also add a domain for Apply on as Closing Stage is set.
Regards
I modifyed the field Stage(stage_id) instead of Closing Stage(is_closed) in Trigger Fields,it is working now
It does seem to work, for any tasks which is 'not in' a closed stage the kanban status changes to blocked (red)
Ti stai godendo la conversazione? Non leggere soltanto, partecipa anche tu!
Crea un account oggi per scoprire funzionalità esclusive ed entrare a far parte della nostra fantastica community!
Registrati| Post correlati | Risposte | Visualizzazioni | Attività | |
|---|---|---|---|---|
|
|
3
apr 22
|
3744 | ||
|
|
1
nov 25
|
469 | ||
|
|
3
ott 25
|
4249 | ||
|
|
2
set 25
|
1474 | ||
|
|
2
set 25
|
2276 |