In project module I am using Automated Actions to "blocked" task Status
when move Tasks Stages to "Done"
but it no working
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- CRM
- e-Commerce
- Comptabilité
- Inventaire
- PoS
- Projet
- MRP
Cette question a été signalée
Hi,
You have almost done it. You have to use the field Stage(stage_id) instead of Closing Stage(is_closed) in Trigger Fields. Also add a domain for Apply on as Closing Stage is set.
Regards
I modifyed the field Stage(stage_id) instead of Closing Stage(is_closed) in Trigger Fields,it is working now
It does seem to work, for any tasks which is 'not in' a closed stage the kanban status changes to blocked (red)
Vous appréciez la discussion ? Ne vous contentez pas de lire, rejoignez-nous !
Créez un compte dès aujourd'hui pour profiter de fonctionnalités exclusives et échanger avec notre formidable communauté !
S'inscrire| Publications associées | Réponses | Vues | Activité | |
|---|---|---|---|---|
|
|
3
avr. 22
|
3747 | ||
|
|
1
nov. 25
|
475 | ||
|
|
3
oct. 25
|
4252 | ||
|
|
2
sept. 25
|
1479 | ||
|
|
2
sept. 25
|
2277 |