In project module I am using Automated Actions to "blocked" task Status
when move Tasks Stages to "Done"
but it no working
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- 客户关系管理
- e-Commerce
- 会计
- 库存
- PoS
- Project
- MRP
此问题已终结
2
回复
3390
查看
Hi,
You have almost done it. You have to use the field Stage(stage_id) instead of Closing Stage(is_closed) in Trigger Fields. Also add a domain for Apply on as Closing Stage is set.
Regards
I modifyed the field Stage(stage_id) instead of Closing Stage(is_closed) in Trigger Fields,it is working now
It does seem to work, for any tasks which is 'not in' a closed stage the kanban status changes to blocked (red)