I'm currently using MRP in v15 Enterprise version.

Now I'm trying to set up routing, but cannot find any places described in Help, which says Routings is under Work Orders in the Manufacture app setting. 


I also tried to find other parts like BoM, work centers, etc.

Avatar
Abbandona

Please check that the functionality has been enabled in the settings

Risposta migliore

Work center routings are configured in the 'Operations' tab on a BOM.

Do ensure that work order functionality has been enabled Settings > Manufacturing > Work Orders

Avatar
Abbandona
Autore Risposta migliore

Thank you for your comment. I'll try to configure.

I was wondering if we can manage half-product inventory management based on each step of work.

Avatar
Abbandona

Yes, it is possible if you define and manage the half-product as a ‘storable product’ with associated BOM.
You would end up with a multi level BOM

Post correlati Risposte Visualizzazioni Attività
0
feb 24
1950
1
nov 23
2174
0
set 23
1717
1
giu 23
3394
0
giu 22
3518