I'm currently using MRP in v15 Enterprise version.

Now I'm trying to set up routing, but cannot find any places described in Help, which says Routings is under Work Orders in the Manufacture app setting. 


I also tried to find other parts like BoM, work centers, etc.

Avatar
Zrušit

Please check that the functionality has been enabled in the settings

Nejlepší odpověď

Work center routings are configured in the 'Operations' tab on a BOM.

Do ensure that work order functionality has been enabled Settings > Manufacturing > Work Orders

Avatar
Zrušit
Autor Nejlepší odpověď

Thank you for your comment. I'll try to configure.

I was wondering if we can manage half-product inventory management based on each step of work.

Avatar
Zrušit

Yes, it is possible if you define and manage the half-product as a ‘storable product’ with associated BOM.
You would end up with a multi level BOM

Related Posts Odpovědi Zobrazení Aktivita
0
úno 24
1840
1
lis 23
2071
0
zář 23
1633
1
čvn 23
3268
0
čvn 22
3433