Dear All,

I have a product with many subassemblies (multi-level BOMs); meaning Product A consistes of B, B consistes of C, C consistes of D and so on; The creation of all MOs works, but I would like to consider available stock at any location before a MO is created. Means, when I already have 100 of B, I won't need the MO for Product B and below, but the MO for Product A just takes the stock of Product B.

Any idea how I can set up the routing that available stock is considered?

Thanks in advance!

Philipp

Avatar
Abbandona

Philipp,

Did you ever figure this problem out?  We are on Odoo 13 and headed towards Odoo 16 but it doesn't appear that Odoo 16 can handle multi-level BOMs with values/attributes in the 2nd level.

Risposta migliore

You can consider your product as a Make to Stock so it will always check stock first. And if stock haven't enough stock it creates related MO or PO, ...
Documentation : Documentation 

Avatar
Abbandona
Post correlati Risposte Visualizzazioni Attività
2
giu 25
1146
0
lug 24
5591
0
feb 24
524
2
ago 16
4417
1
lug 16
3783