Suppose I have created one task, and It has completed 20%, how to get this percentage?
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- CRM
- e-Commerce
- Contabilità
- Magazzino
- PoS
- Project
- MRP
La domanda è stata contrassegnata
1
Rispondi
2371
Visualizzazioni
Hi,
Didn't get what exactly you are looking for, if you are looking for the percent of progress of each task, if you switch to the task tree view, you can see this, this is also there in the form view, this is based on the Planned Hours and recorded time.