Suppose I have created one task, and It has completed 20%, how to get this percentage?

Awatar
Odrzuć
Najlepsza odpowiedź

Hi,

Didn't get what exactly you are looking for, if you are looking for the percent of progress of each task, if you switch to the task tree view, you can see this, this is also there in the form view, this is based on the Planned Hours and recorded time.