Hi,


We have created a route where:

» Step 1: We receive our purchase in Location 1

» Step 2: This is moved to Location 2, it takes 2 days 

» Step 3: From Location 2, it's moved to location 3, it takes 3 days


Scheduled/Effective dates are correctly set for the transfers created for step 2 and 3.


However, if we update the Schedled/Effective date from the parent transfer, dates are not updated in the child ones created for step 2 and 3.


Is there a configuration or module that could be setup or installed to get the dates updated for the child transfers?


Thanks!