When contracting services or long lead special items most companies use a milestone billing to manage the program. Is there any way to achieve this from the vendor perspective. I know the project app allows for this feature but only towards the sales orders. We would want this based on time and material from the vendor or a % base of the total contract value.

Avatar
Descartar
Mejor respuesta

This is also possible from the Vendor Perspective.


By default, a Service Product has a Vendor Bill Control Policy (on the  Product -->  Purchase tab) of "On received quantities" which requires the User who signs off on the Service Milestone to update the Purchase Order line:



You can also set the Control Policy to "On ordered quantities":

  • You can then just enter each Milestone Vendor Bill when you receive it.
  • You don't need to update the Purchase Order Received Quantity.
  • You should have another way to verify and document that the Service was completed.


We recommend the default, since there is a Chatter message below the Purchase Order showing WHO signed off on the Service Milestone and WHEN this was done:


Note: Here I have also created a Unit of Measure "Milestones" but you can also use the default UoM of "Units" if that will make sense to your Vendor(s).


I have also seen Customers create PO lines like this:


They would update (or not) the PO as discussed with the same options above, and during Billing for 40% complete do something like this on the Vendor Bill line:

This would allow you to pay your Vendor $600.