Hello All I am using Odoo 16.

I am trying to refine the workflow in my shop for a manufactured and subcontracted product. For the example I am going to call this product "QC-BOX"

I have created 6 parts with the same prefix and different suffix.

the part name are like this as shown below:

part name consumed in which bill of material  BOM type routes
QC-box-programmed QC-box-cut MFG MTO
QC-box-cut QC-box-bend MFG MTO
QC-box-bend QC-box-welded MFG MTO
QC-box-welded QC-box-painted MFG MTO
QC-box-painted QC-box-final SUB-CONTRACTING RESUPPLY TO CONTRACTOR
QC-box-final this is the top level assembly ASSEMBLY MTO



Now My ideal work-flow is to create a sales order and put the top level assembly which is "QC-box-final" on the sales order and confirm the sales order and it should create an MO linked to the sales order since the route for that product is Make to order and that bill of material require the painted version of the product so now that PO is also generated upon creation of the top assembly MO. Now in order to supply the part to the contractor, we need to prepare the welded part of the box, then to make the welded part, we need bended part and till the programmed version. 

The problem is after the creation of the PO, it does not create any demand for the welded part to be made so the cycle stops after the creation of the PO for the painted part. There should be demand for all the children parts one after another in order to create the part to supply to the contractor. All the product have reordering rule set, trigger is auto and the lead time for the manufacturing in all product is 60 days (just to make sure it triggers demand).

Any help would be appreciated!

Avatar
Descartar
Autor Mejor respuesta

Hello, Thanks for the reply. Can you be more specific about the routes and and rule on the Welded part and painted parts, I am struggling to get this work-flow right. I am only getting success in the creation of MO of the final assembly. Also How my subcontracting route and operation should be set, is there any thing to watch out for? we are using sub-contracting but it is not multilevel assembly, we just supply raw material and that works just fine. Thank again for the help

What type of route to be selected Painted Part number? Thank

Avatar
Descartar

The material that is being supplied to the subcontractor need to have the route resupply subcontractor on order enabled.

Mejor respuesta

Believe you need to enable the route Resupply subcontractor on Order for product QC-box-welde. That should trigger creation of an MO for QC-box-welded (as you have replenishment configured) 

Updated-

part name consumed in which bill of material  BOM type routes
QC-box-programmed QC-box-cut MFG MTO
QC-box-cut QC-box-bend MFG MTO
QC-box-bend QC-box-welded MFG MTO
QC-box-welded QC-box-painted MFG RESUPPLY TO CONTRACTOR
QC-box-painted QC-box-final SUB-CONTRACTING  
QC-box-final this is the top level assembly ASSEMBLY MTO