Hello everyone,

Let's say that I manufacture products that usually have more than 100+ components. I defined the BOM list to ODOO. The problem is, I want to start manufacturing when some of the components are available in the warehouse, not all of it. And the first available components will not be the same every time. For example, this month i will start manufacturing product A with components 5, 10, 12 and 15. Next month, I  will start with 4, 7 and 10. As the other components arrive, I continue to manufacture until all of the BOM is completed. Is there a way to do it without dividing product to certain subparts ?  You can think it as a puzzle and the pieces arrive at different times. To prevent delay, you have to start doing it with what you have at the moment.