Ir al contenido
Menú
Se marcó esta pregunta
1 Responder
2025 Vistas

Hi

example:

from PRODUCT1 are there 1000 pcs under " Request for Quotations "

and there is MO that needs 2000 pcs of PRODUCT1

... after ....  run schedulers ...there is new quotation generated of PRODUCT1 with 2000 pcs

so the 1000 pcs still under quotations is not used to generate new quotations , that in this case must be

1000 pcs instead of the 2000 pcs

is there module or setting to fix this ?


Avatar
Descartar
Autor Mejor respuesta


Avatar
Descartar