My company sells a variety of sweets. By feel, we anticipate some of the stocks guessing an amount that our regular customers will order, and then we finish with small batches if needed after the sale order is confirmed.


On the one hand, if we want to have a Make to Stock route so that we can anticipate that amount, but if we did not anticipate enough, and we are short on stock when the sales order is created, we want to have the rest made by the Make to Order rule. 

The problem is that even if we have that anticipated stock, the MTO rule will create a production order without accounting that stock, hence telling us to produce extra quantity.


How would you mix both rules to work on my case?


Thanks

Avatar
Descartar
Mejor respuesta

I would not use MTO at all.  When you get the order, there will be a requirement to fill up your stock. Set a reordering rule with 0 stock as minimum.  Use MPS to to set prognoses and produce for stock before you get the order.

Mixing MTO and MTS will get you into difficulties and a lot of manuale adjustments of orders etc. 

Avatar
Descartar
Autor Mejor respuesta

Yes! That did work as expected. Thank you so much.

By the way, I'm using community so I don't have MPS. Is there any alternative to this that you know?