Ir al contenido
Menú
Se marcó esta pregunta
1 Responder
1832 Vistas

On OE 16 for each BOM on the Miscelaneous Tab you have the option to make the manufacturing order when all components are ready or when components for the first operation are ready.

I could not find any way to tell the system which components belong to which operation

Any suggestion is welcome

Regards

Maurice

Avatar
Descartar
Mejor respuesta

Also looking for this info..?

Found it is set on the BOM component tab, by using the modify list view option to Consumed in Operation, then editing that field.

Avatar
Descartar
Publicaciones relacionadas Respuestas Vistas Actividad
1
jun 21
1492
1
ago 24
1324
2
ago 25
1433
1
jul 24
2217
1
ene 24
2296