Hello. We manufacture custom steel wheels. The production process includes 8 operations. The question is whether it is possible to take into account the quantity rather than the time of the task when ordering. For example, there is a wheel and 8 meters of welding seam are needed for its production. When creating an order, the order for the welding station displays 1 wheel, but it is necessary that there be 8 meters of welding seam.