In the documentation there is a mode tag that can be added to a gantt view. This tag allows you to scale the time duration of the gantt view. But it doesn't seem to do anything in reality.

https://doc.openerp.com/trunk/server/03_module_dev_03/#id1

<gantt date_stop="date_finished" date_start="date_start" string="Productions" default_group_by="routing_id" mode ="month">
                </gantt>

This code isn't rejected as an XML error, but it doesn't seem to scale the gantt view.

How can you change the scale of a gantt view?

الصورة الرمزية
إهمال

Do not works for me too : OpenERP 7

أفضل إجابة

The below code is working in openerp 7

<record id="view_project_gantt" model="ir.ui.view">
    <field name="name">Project Gantt</field>
    <field name="model">project.test</field>
    <field name="type">calendar</field>
    <field name="arch" type="xml">
    <gantt date_stop="date_finished" date_start="date_start" string="Productions" default_group_by="routing_id" mode ="month">
        </gantt>
    </field>

</record>

    <record id="action_project_test" model="ir.actions.act_window">
            <field name="name">Project Test</field>
            <field name="res_model">project.test</field>
            <field name="view_type">form</field>
            <field name="view_mode">tree,form,gantt</field>     
    </record>
الصورة الرمزية
إهمال
الكاتب

no it does not, the scale does not change. Try changing mode to day or 3weeks.

أفضل إجابة
  1. List item
  2. List item
  3. List item
  4. List item
الصورة الرمزية
إهمال
المنشورات ذات الصلة الردود أدوات العرض النشاط
2
فبراير 19
6755
3
فبراير 24
11794
0
مارس 15
2260
4
يناير 24
23266
Attrs attribute تم الحل
2
يناير 24
2555