Siirry sisältöön
Menu
Sinun on rekisteröidyttävä, jotta voit olla vuorovaikutuksessa yhteisön kanssa.
Tämä kysymys on merkitty
2 Vastaukset
8646 Näkymät

In the documentation there is a mode tag that can be added to a gantt view. This tag allows you to scale the time duration of the gantt view. But it doesn't seem to do anything in reality.

https://doc.openerp.com/trunk/server/03_module_dev_03/#id1

<gantt date_stop="date_finished" date_start="date_start" string="Productions" default_group_by="routing_id" mode ="month">
                </gantt>

This code isn't rejected as an XML error, but it doesn't seem to scale the gantt view.

How can you change the scale of a gantt view?

Avatar
Hylkää

Do not works for me too : OpenERP 7

Paras vastaus

The below code is working in openerp 7

<record id="view_project_gantt" model="ir.ui.view">
    <field name="name">Project Gantt</field>
    <field name="model">project.test</field>
    <field name="type">calendar</field>
    <field name="arch" type="xml">
    <gantt date_stop="date_finished" date_start="date_start" string="Productions" default_group_by="routing_id" mode ="month">
        </gantt>
    </field>

</record>

    <record id="action_project_test" model="ir.actions.act_window">
            <field name="name">Project Test</field>
            <field name="res_model">project.test</field>
            <field name="view_type">form</field>
            <field name="view_mode">tree,form,gantt</field>     
    </record>
Avatar
Hylkää
Tekijä

no it does not, the scale does not change. Try changing mode to day or 3weeks.

Paras vastaus
  1. List item
  2. List item
  3. List item
  4. List item
Avatar
Hylkää
Aiheeseen liittyviä artikkeleita Vastaukset Näkymät Toimenpide
2
helmik. 19
6776
3
helmik. 24
11848
0
maalisk. 15
2260
4
tammik. 24
23382
2
tammik. 24
2591